Planning IT-Grundschutz effort internally: capacity by role and work package

You plan the internal effort of an IT-Grundschutz project by role and work package: who is needed at which step, and which quantities determine how much work falls to these roles? Under BSI Standard 300-1 of the Bundesamt für Sicherheit in der Informationstechnik (BSI), the German Federal Office for Information Security, top management releases the resources (ch. 2.10), and with GC.8.1 the user catalogue (Anwenderkatalog) requires a procedure for resource planning. This page provides a capacity plan for this with roles, ten work packages, the quantity drivers and a fictitious, fully worked example. It deliberately contains no prices, person-days or durations.

Dark wooden peg planning board on the wall of a project room, rows of brass and dark blue pegs forming bars of different lengths, with a dish of loose pegs below

Why this plan works without person-days

Neither BSI Standard 300-1 nor the user catalogue states an effort for a Grundschutz project. The catalogue does assign an effort level to each requirement, and the namespace describes the levels with rough time frames per requirement, for example „innerhalb einer Woche“ (our translation: "within one week") for level 2. No figure for the whole project follows from this, because quantities, parallel work and existing safeguards are missing. How much work arises depends on quantities that only the survey delivers: business processes, protection requirements, assets, sites, service providers, quality of the existing documentation. A figure before this survey would be an estimate without a basis.

A great deal can still be planned. You can define which roles the project needs, in which work package each role leads, contributes or decides, and which quantities you have to survey first in order to assess the load per role. That is the content of the capacity plan below. It serves as the basis for the decision paper on releasing resources and can be updated as soon as the quantities are known.

What 300-1 and the catalogue require on resources

The requirements on resources are spread across the standard and the practices (Praktiken) GC and UMS. The table summarises them and shows what follows for planning.

ReferenceRequirement (summary or wording)Consequence for the capacity plan
300-1, ch. 2.10Responsibility for the ISMS lies with top management and cannot be delegated. The decision papers submitted to it „insbesondere“ (our translation: "in particular") include the release of resourcesThe plan ends in a decision paper to top management
300-1, ch. 4.4Points to consider include providing the necessary resources, the competences of those responsible and realistic deadlines. Top management approves the approach „da diese die erforderlichen Ressourcen bereitstellen muss“ (our translation: "since it has to provide the necessary resources")Plan a second approval for the implementation phase
300-1, ch. 2.1.2Lack of resources is one of the internal factors of the contextRecord known bottlenecks already in the context analysis
300-1, ch. 2.6Recommendation to start a first implementation with the most important business process of the highest protection requirements category. All business processes are to be examined successivelyPlan capacity per cycle, not for all business processes at once
300-1, ch. 5.2.1For the internal audit programme, financial and time resources are to be determined, among others for audit activities, audit methods and the availability of audit staffAudit team as a separate role with its own capacity
GC.8.1 (MUSS, i.e. MUST)„Governance und Compliance MUSS ein Verfahren zur kontinuierlichen, wirtschaftlichen Planung von Ressourcen für das ISMS verankern.“ (our translation: "Governance and Compliance MUST establish a procedure for continuous, economical planning of resources for the ISMS.") According to the guidance, this covers personnel, financial and material or technical resourcesThe plan is updated continuously, not drawn up once
GC.9.1.1.1.1 (MUSS)„Governance und Compliance MUSS dem Informationssicherheitsbeauftragten hinreichende Ressourcen zuweisen.“ (our translation: "Governance and Compliance MUST allocate sufficient resources to the information security officer.") According to the guidance, in small institutions the information security officer (ISB) can perform the task alongside others if there is enough time and no conflict of interestDefine the ISB's share of working time explicitly
GC.9.1.1.2, GC.9.1.1.4 (MUSS)Deputy arrangements for all relevant roles. Requirements and skills for each role and responsibility holderDeputy and qualification per role in the plan
UMS.2.2, UMS.3.1, UMS.4.1 (MUSS)Prioritisation based on risk assessment, dependencies and availability of resources. Clearly assigned persons responsible. Realistic target dateCapacity is a prioritisation criterion, and deadlines follow from it

The roles in a Grundschutz project

Planning is by role, not by person. One person can hold several roles, except where 300-1 rules out conflicts of interest: between head of IT and ISB and between data protection officer and ISB (ch. 2.8), between implementation and progress tracking (ch. 4.5), and for the internal audit team, whose selection is meant to ensure objectivity and impartiality (ch. 5.2.2). Which role is responsible for which decision and which evidence, and how you resolve conflicts, is set out on the page Roles and responsibilities. Here the only question is how heavily each role is tied up in the project.

Responsibilities per decision and evidence: Roles and responsibilities.

RoleTasks in the projectReferenceNote on staffing
R1 Top managementDecisions and approvals: scope, protection requirements, order, resources, policy, framework for risk assessment, residual risksCh. 2.10, 2.11, 4.2.3Reserve dates for decisions in the calendar early
R2 Information security officerSteering the project, drafts, moderating the risk assessment, reports to top managementGC.9.1.1.1; guidance on GC.9.1.1.1reports directly to top management; not also head of IT
R3 Internal coordinationDates, documents, filing, following up open pointsown recommendationcan sit with the ISB in small projects
R4 Business process ownersProcess description, protection requirements, risk ownership, approval of the implementation planning for their risksCh. 2.5, 2.6, 4.2.1; Annex 3, criteria 16 and 31one person per business process
R5 IT operations and administratorsAsset data, implementation status of technical requirements, operational implementation, technical evidenceCh. 3.2, 4.1, 4.4heavily tied up in AP-05, AP-07 and AP-09
R6 Business units and other functionsFacilities, HR, procurement, development: status of their requirements and implementationCh. 4.4 (coordination with affected areas)name one responsible function per practice
R7 Data protection and complianceCompliance obligations, coordination of the policy, interfacesCh. 2.2, 2.8data protection officer role kept separate from the ISB
R8 Progress trackingStatus of the implementation plan, deviations, status reportsCh. 4.5not the same person who implements the safeguards
R9 Internal audit teamAudit programme, internal audits, report to top managementCh. 5.2; PERF.3.1independent of those who built the ISMS
R10 Service providersInformation and evidence on outsourced partsCh. 3.1 (outsourcing boundaries)clarify their contribution contractually before AP-05 starts

Ten work packages along the five process steps

The work packages (AP, from the German Arbeitspaket) follow the chapters of 300-1 and apply when an ISMS is set up from scratch. For moving an existing ISMS, the Migration page has its own breakdown into ten packages, for example with the transfer of an IT-Grundschutz Check. The numbers there do not match those on this page. The column "Quantity drivers" names what determines the size of the package.

APContentResultQuantity driversChapter
AP-01Context, compliance obligations, scope, interested partiesContext note, register of obligations, decision paper on scopeNumber of organisational units and sites, number of obligations2.1 to 2.4, 2.10
AP-02Identify business processes, determine protection requirements, set the orderProcess list with protection requirements, decision paperNumber of business processes; process map available or not2.5, 2.6, Annex 2
AP-03Policy, roles, communication, document controlapproved policy, organisation document, control procedureexisting documents, number of roles2.7 to 2.9
AP-04Framework for risk assessment: procedure, criteria, risk appetite, rolesRisk analysis guideline, authorisation by top managementexisting method, e.g. under 200-3 or ISO/IEC 270052.11, Annex 3
AP-05Delimit the information domain, record assets and dependenciesAsset register with dependencies and interfacesNumber of assets, quality of CMDB and network plan, number of processes with high protection requirements, outsourcing3.1, 3.2
AP-06Select blueprints (Blaupausen), assign target object categories (Zielobjektkategorien), specify parametersRequirements package with catalogue versionNumber of target object categories, number of parameters3.3 to 3.5
AP-07Survey and assess the implementation status per requirementStatus with justification, classification of SOLLTE (SHOULD) requirements not fulfilledNumber of requirements in the package, number of responsible functions4.1
AP-08Carry out the risk assessmentRisk register, treatment decisions, approvalsProcesses with high protection requirements, assets not covered, SOLLTE requirements permanently not fulfilled4.2
AP-09Implementation plan, responsibilities, deadlines, progress trackingprioritised implementation plan with evidenceNumber of open requirements and their effort levels4.3 to 4.5
AP-10Performance evaluation, internal audit, management review, improvementAudit report, management report, correction and improvement planExtent of the audit programme under ch. 5.2.1, e.g. information systems, sites, persons affected5, 6

The transition from an existing setup is described by the work packages on the Migration page. What AP-01 to AP-04 look like in a case followed from start to finish is shown in the case file, part 1.

Matrix with ten work packages AP-01 to AP-10 as rows and the roles top management, information security officer (ISB), process owners, IT operations, business units, progress tracking and audit team as columns. The cells show L for leads, C for contributes, D for decides and I for informed. To the left of the rows, the process steps of 300-1 are marked as a band: step 1 survey and planning, step 2 requirements analysis, step 3 implementation, steps 4 and 5. A note below the matrix says that 7 of the 10 roles are shown and that coordination, data protection and compliance, and service providers are in the table.
Capacity plan as a role matrix per work package. Own illustration based on BSI Standard 300-1, version 1.0 of 20 October 2026; without quantities or timings.

Capacity plan: who is needed in which work package

The matrix is the actual work result. L means leads, C contributes, D decides or approves, I is informed. An empty cell means the role is not needed. The allocation is our proposal and is tied to the references in 300-1 where the standard names a role.

APR1 Top managementR2 ISBR3 CoordinationR4 Process ownersR5 IT operationsR6 Business unitsR7 Data protection, complianceR8 ProgressR9 Audit teamR10 Service providers
AP-01DLCCICC
AP-02DLCCICI
AP-03DLCIIIC
AP-04DLCCIC
AP-05ILCCCCC
AP-06ILCICI
AP-07ILCCCCCC
AP-08DLCDCCC
AP-09DLCDCCCC
AP-10DCCCCCCCL

Two ways of reading it help with planning. The columns show which role is tied up across the whole project: ISB and coordination throughout, IT operations mainly in AP-05 to AP-09. The rows with a D for R1 show where the project waits for a top management meeting. The D for R4 in AP-08 and AP-09 stands for the authorisation of the implementation planning by the risk owners (Annex 3, criterion 31), while approval of residual risks stays with top management (criterion 30).

What determines the size: surveying the quantity drivers

Before you assess the load per role, survey the quantities. Most of them are available after AP-01 and AP-02, the number of requirements after AP-06. The table shows where each driver acts and where you get it from.

Quantity driveraffectsSourceWhy it counts
Business processes in scopeAP-02, AP-05, AP-07Process map or simplified analysis under Annex 2Protection requirements per business process (ch. 2.6); each cycle starts with one process
of which with high protection requirementsAP-05, AP-08Result of AP-02Document dependencies on the business process (ch. 3.2) and explicit risk assessment (ch. 2.11)
Assets and their data sourcesAP-05, AP-06CMDB, asset register, network plan, operating manuals300-1 allows existing sources to be used (ch. 3.1); their quality decides how much has to be surveyed again
Target object categories and requirements in the packageAP-06, AP-07, AP-09Result of AP-06Every requirement needs a status (ch. 4.1.1)
Distribution of effort levels in the packageAP-09Field effort_level in the catalogueshows how many requirements are quick wins (level 1) and how many are elaborate, complex safeguards (level 5)
SitesAP-01, AP-05, AP-10ScopeSite inspections, facility requirements, extent of the audit programme (ch. 5.2.1)
key service providers and outsourcingAP-05, AP-07Contracts, outsourcing registerOutsourcing boundaries (ch. 3.1); status depends on information from third parties
Existing setupallexisting ISMS under the 2023 Compendium or ISO/IEC 27001shortens some packages but requires a comparison in return; see Migration

For the distribution of effort levels, the catalogue itself gives a point of reference. In the build of 29 October 2026, of the 99 requirements of the methodology and risk management, 79 have level 0, which according to the namespace is not rated because implementation is mandatory in every case. For the 901 requirements from the kernel, the levels are distributed as follows: 0: 69, 1: 44, 2: 166, 3: 275, 4: 158, 5: 189 (own count). Your own package will have a different distribution; count again after AP-06.

Fully worked example (fictitious)

Muster Software GmbH (entirely made up) develops a specialist application for public-sector clients and runs it in its own data centre. Surveyed in AP-01 and AP-02: six business processes in scope, two of them with high protection requirements; two sites; three key service providers; a CMDB in which the mapping of applications to systems is missing for about half of the systems; no ISMS under the 2023 Compendium. Top management has decided to start with the business process "Operating the Musterakte", the operation of the specialist application.

The table shows the estimated load per role in the first cycle on three levels: high, medium, low. The levels are meant relative to each other and do not replace planning in hours. They show where bottlenecks are to be expected and for what top management has to release capacity.

APQuantities in the exampleISBProcess ownerIT operationsTop managementBottleneck and countermeasure
AP-011 institution, 2 sites, obligations from contracts with clientshighlowlowmediumContract documents are held by sales; name a contact person
AP-026 processes, no process maphighmediumlowmediumsimplified analysis under Annex 2 in one workshop per area
AP-03no policy in placehighlowlowmediumschedule coordination with data protection and staff representatives early
AP-04no risk method in placehighmediumlowmediumalign the method with the 35 minimum criteria (Mindestkriterien)
AP-05first process with high protection requirements, CMDB incompletemediummediumhighlowIT operations is also fully loaded with day-to-day operations; agree fixed time slots
AP-06Package for the first processhighlowmediumlow-
AP-07Status per requirement, three service providers required to provide informationhighmediumhighlowrequest information from the service providers in advance
AP-08Risk assessment for the first processhighhighmediummediumProcess owner is the risk owner and has to assess personally
AP-09Implementation plan for the open requirementsmediummediumhighmediumprogress tracking with the ISB, implementation with IT operations (ch. 4.5); because the ISB is under high load overall, controlling takes over the monthly status compilation
AP-10internal audit of the first cyclemediumlowmediummediumstaff the audit team independently, internally or externally

Result for the decision paper: The ISB is under high load in seven of ten packages. The guidance on GC.9.1.1.1.1 only allows the role to be performed alongside other duties if enough time remains for the tasks. The paper therefore proposes a fixed share of the ISB's working time for the project and names a deputy (GC.9.1.1.2). IT operations is the bottleneck in AP-05, AP-07 and AP-09. The paper proposes fixed time slots and points out that prioritisation under UMS.2.2 has to take the availability of resources into account. The remaining five business processes follow in later cycles with their own capacity planning.

Checklist: the release of resources as a decision paper

The paper to top management should be structured so that top management can decide on capacity without knowing the methodology in detail. These points belong in it:

  1. Size of the cycle: business process, scope, sites (ch. 2.3, 2.6)
  2. Roles with staffing, deputy and required qualification (GC.9.1.1.2, GC.9.1.1.4)
  3. Capacity plan: role matrix and load levels per work package
  4. quantity drivers surveyed and the assumptions still open
  5. Bottlenecks with countermeasure, explicitly the ISB's share of working time (GC.9.1.1.1.1)
  6. Conflicts of interest and how they are avoided (ch. 2.8, 4.5; GC.9.1.1.3)
  7. where external support is planned and for what
  8. material and technical resources, for example tools for asset recording or ISMS documentation (guidance on GC.8.1)
  9. When the plan is updated, for example with every status report under ch. 4.5 and in the management review under ch. 5.3
  10. Proposed resolution

Record the resolution in documented form like the other top management decisions under chapter 2.10. A separate paper follows for the implementation phase, because top management approves the approach separately under chapter 4.4.

Planning external support

External support relieves individual roles; responsibility stays where it is. For the ISMS it lies with top management (ch. 2.10), and process owners remain the risk owners of their risks. Tasks that can be given to external parties include preparing decision papers, moderation and methodology, checking an existing risk method against Annex 3, or an internal audit if the audit team is independent of the set-up work.

Blackfort Technology supports you with the decision and transition planning through a decision paper that includes the resource requirements, with the readiness analysis and migration concept, and with implementation. We set scope and price in a quote after an initial meeting; we do not state prices on this website. Blackfort Technology describes the role of the external information security officer on its company website.

Services: Consulting on IT-Grundschutz and Grundschutz++, Readiness and migration concept. External ISB: https://www.blackfort-tec.de/en.

Rights notice: Quotations from BSI Standard 300-1 (source: BSI page on Grundschutz++) are © Bundesamt für Sicherheit in der Informationstechnik and are not licensed under CC BY-SA 4.0. The licence notice at the end of the page applies only to the extracts from the catalogue data.

Frequently asked questions

How much effort does IT-Grundschutz take?
There is no general figure; neither BSI Standard 300-1 nor the user catalogue gives one. The effort depends on quantities such as the number of business processes and of those with high protection requirements, the number of assets and sites, the key service providers and the quality of existing documentation. Survey these quantities first, then plan per role and work package.
Who releases the resources for a Grundschutz project?
Top management. 300-1 lists the release of resources among the decision papers in chapter 2.10. Top management approves the approach to implementation under chapter 4.4, because it has to provide the resources.
Can the information security officer look after the project alongside other work?
According to the guidance on GC.9.1.1.1.1, in small institutions the ISB can perform the task alongside other duties if enough time remains and there is no conflict of interest. The requirement itself is a MUSS requirement: the ISB must receive sufficient resources. Record the share of working time explicitly for this reason.
Which roles does a Grundschutz project need at a minimum?
Top management, ISB, owners of the business processes under consideration and IT operations are needed in every cycle. In addition, there is progress tracking, which under 300-1 should not lie with the person implementing (ch. 4.5), and an independent internal audit team (ch. 5.2.2).

Get in touch

Discuss your project

Briefly describe where you stand. In a free initial call we work out what you need.

Request an initial call

Sources

Quotations from BSI standards and BSI web pages are © Federal Office for Information Security (BSI) and are reproduced verbatim, in quotation marks and with source reference. This is an independent offering, not an offering of the BSI.

Last updated
2026-11-06
Technically reviewed
2026-11-06
Catalogue version
Grundschutz++ user catalogue, build 2026-10-29 (State-of-the-Art Library, commit c3f37859 of 2026-10-30)

Licence notice

This page contains excerpts from catalogue data published by the German Federal Office for Information Security (BSI), licensed under CC BY-SA 4.0. The excerpts are shared under the same licence. This licence covers only these catalogue excerpts; quotations from BSI standards are © BSI and reproduced as quotations with source reference.